Seattle Parks & Rec Playfield Projects Schedule (February 2025)

Smith Cove Playfield

Project Approved: 2015

Budgeted: Yes

Funding Sorce: Parks Department

Design: 2016-2019

Project Manager: Janice Liang

Project Type: improve existing grass playfield; no lights

Construction Schedule: Start September 2025; reopen early summer 2027.

Seattle Parks & Recreation Department Athletic Fields Upgrade Projects List

Georgetown Playfield

Year Approved: 2008

Schedule: Started October 2007, Completed June 2008

Funding Source: Proparks 2000

Lighted: Yes

Synthetic: Yes

Field upgrade: Turf replaced Summer 2022

Genesee Playfields