Seattle Parks & Rec Playfield Projects Schedule (February 2025)
Smith Cove Playfield
Project Approved: 2015
Budgeted: Yes
Funding Sorce: Parks Department
Design: 2016-2019
Project Manager: Janice Liang
Project Type: improve existing grass playfield; no lights
Construction Schedule: Start September 2025; reopen early summer 2027.
Seattle Parks & Recreation Department Athletic Fields Upgrade Projects List
Georgetown Playfield
Year Approved: 2008
Schedule: Started October 2007, Completed June 2008
Funding Source: Proparks 2000
Lighted: Yes
Synthetic: Yes
Field upgrade: Turf replaced Summer 2022